Real Estate Development Agreement Disputes: Key Legal Issues

Real estate development agreements can determine whether a commercial project moves forward as planned, becomes delayed by regulatory or financing problems, or ends in litigation. Developers, property owners, investors, cities, counties, lenders, and other project participants may rely on development agreements to allocate rights involving land use, construction timing, infrastructure, public improvements, approvals, financing, transfers, and long-term project obligations. When those expectations diverge, the resulting dispute can affect the entire value and feasibility of the development.

In California, the term “development agreement” can describe different types of arrangements. Government Code Sections 65864 through 65869.5 authorize formal statutory development agreements between local governments and persons holding legal or equitable interests in real property. Private parties may also enter separate development, development-management, cost-sharing, infrastructure, or project agreements governing their own contractual relationship. Identifying which type of agreement is involved is essential because the procedures, remedies, deadlines, and legal standards can differ substantially.

Statutory and Private Development Agreements Should Be Distinguished

A statutory California development agreement generally involves a city, county, or city and county and is adopted under Government Code Section 65864 and the sections that follow it.

A private development agreement may instead be entered between parties such as:

  • A property owner and developer;
  • A landowner and development manager;
  • Joint venture participants;
  • Adjacent property owners;
  • A master developer and parcel developer;
  • A commercial landlord and project developer;
  • A seller and buyer with post-closing development obligations;
  • An infrastructure developer and benefiting owners; or
  • Affiliated entities participating in a larger project.

A project can involve both types simultaneously. For example, a developer may have a statutory agreement with a city establishing development rights while separately operating under a private agreement with investors, landowners, contractors, and lenders.

California Statutory Development Agreements Are Designed to Provide Development Certainty

California’s statutory development agreement framework was enacted in part to provide greater certainty for development projects.

A developer may commit substantial resources toward:

  • Property acquisition;
  • Design;
  • Environmental review;
  • Entitlements;
  • Infrastructure;
  • Public improvements;
  • Utility upgrades;
  • Financing;
  • Construction planning; and
  • Community benefits.

Without some assurance concerning the land use rules governing the project, changing regulations can materially affect the feasibility of a long-term development.

A statutory development agreement can provide contractual protection concerning specified development regulations while also imposing negotiated obligations on the developer.

A Local Government May Enter a Development Agreement With a Person Holding a Property Interest

Government Code Section 65865 authorizes a city, county, or city and county to enter into a development agreement with a person having a legal or equitable interest in real property for development of that property.

This can include parties holding interests such as:

  • Fee ownership;
  • Contractual acquisition rights;
  • Other qualifying equitable interests; or
  • Successor interests recognized under the agreement.

Before relying on a development agreement, the parties should confirm that the applicant possessed the required property interest and that the local agency followed its adopted procedures for considering the agreement.

Required Terms of a Statutory Development Agreement Are Important

Government Code Section 65865.2 requires a statutory development agreement to address several core subjects.

The agreement must specify matters including:

  • The duration of the agreement;
  • The permitted uses of the property;
  • The density or intensity of use;
  • The maximum height and size of proposed buildings; and
  • Provisions concerning reservation or dedication of land for public purposes.

The agreement may also include other conditions, restrictions, and requirements concerning subsequent discretionary actions.

These negotiated provisions frequently become the basis of later disputes over exactly what the developer secured and what obligations remain subject to future government review.

Development Agreements Can Address Project Timing

A statutory development agreement may establish dates or periods for commencing construction and completing the project or individual phases.

Timing provisions can become important when development is delayed by:

  • Financing problems;
  • Market changes;
  • Litigation;
  • Environmental review;
  • Utility limitations;
  • Government processing;
  • Contractor disputes;
  • Material shortages;
  • Interest rate changes;
  • Tenant requirements; or
  • Other project conditions.

The agreement should be reviewed for extension rights, force majeure provisions, tolling provisions, amendment procedures, and consequences of missing contractual milestones.

Public Infrastructure Obligations Can Become Major Sources of Conflict

Development agreements frequently allocate responsibility for infrastructure needed to support a project.

Potential obligations may involve:

  • Road improvements;
  • Traffic signals;
  • Water facilities;
  • Sewer facilities;
  • Stormwater systems;
  • Utilities;
  • Parks;
  • Pedestrian improvements;
  • Transit improvements;
  • Public safety facilities;
  • Drainage systems; and
  • Other public improvements.

Government Code Section 65865.2 specifically permits development agreements to include terms relating to developer financing of necessary public facilities and reimbursement over time.

Disputes may arise over who must construct the improvement, when construction is required, how costs are allocated, whether reimbursement conditions have been satisfied, and whether later project phases must contribute.

Reimbursement Rights Should Be Defined Precisely

A developer may fund infrastructure that benefits property owned by other parties or supports later development phases.

The agreement may provide for reimbursement through:

  • Future development fees;
  • Payments from later developers;
  • Reimbursement agreements;
  • Assessment districts;
  • Community facilities districts;
  • Credits against future obligations; or
  • Other financing mechanisms.

Disputes can arise when the developer contends that reimbursement became due but the local agency argues that:

  • Required improvements were incomplete;
  • Costs were not adequately documented;
  • The expenditure exceeded approved amounts;
  • The reimbursement source has not materialized;
  • The agreement imposed additional conditions; or
  • The claimed cost was outside the reimbursable scope.

Development Agreements Can Protect Certain Existing Land Use Rules

Government Code Section 65866 generally provides that, unless the development agreement says otherwise, the rules, regulations, and official policies governing permitted uses, density, and specified design, improvement, and construction standards applicable to the project are those in effect when the agreement is executed.

This can be one of the principal economic benefits of a statutory development agreement.

A developer may invest based on agreed expectations concerning:

  • Permitted use;
  • Density;
  • Development intensity;
  • Building design standards;
  • Improvement requirements;
  • Construction standards; and
  • Other development regulations addressed by the agreement.

A Development Agreement Does Not Freeze Every Law or Government Decision

A statutory development agreement should not be treated as an absolute guarantee that no later rule can ever affect the project.

Government Code Section 65866 allows local governments to apply new rules, regulations, and policies that do not conflict with the rules and policies protected by the agreement.

The statute also does not necessarily eliminate subsequent discretionary governmental decisions.

Disputes therefore often focus on whether a later requirement:

  • Conflicts with the development agreement;
  • Falls outside the agreement’s protected subjects;
  • Is a permissible nonconflicting regulation;
  • Was expressly reserved to future governmental discretion; or
  • Materially prevents development at the agreed use, density, or intensity.

Later State or Federal Law Can Override Contractual Expectations

Government Code Section 65869.5 addresses circumstances where state or federal laws or regulations enacted after execution of the development agreement prevent compliance with one or more contractual provisions.

In that situation, affected provisions must generally be modified or suspended as necessary to comply with the later law.

This can become important when later legislation or regulation affects:

  • Environmental standards;
  • Housing requirements;
  • Building requirements;
  • Water supply;
  • Transportation;
  • Public safety;
  • Climate-related regulations;
  • Accessibility; or
  • Other regulated development matters.

A party generally cannot demand performance of a development agreement term when subsequent controlling law makes that performance legally prohibited.

A Statutory Development Agreement Must Be Approved Through a Public Process

Government Code Section 65867 requires public hearings on a development agreement application before both the planning agency and the legislative body.

Notice must be provided according to the applicable statutory requirements.

This public process can become important when a project is challenged based on alleged procedural defects involving:

  • Notice;
  • Public hearings;
  • Planning commission consideration;
  • Legislative approval;
  • Project description;
  • Concurrent land use approvals; or
  • Other procedural requirements.

A California Development Agreement Is a Legislative Act

Government Code Section 65867.5 expressly provides that a development agreement is a legislative act.

The agreement must be approved by ordinance and is subject to referendum.

This distinguishes statutory development agreements from ordinary private contracts approved only through signatures of the contracting parties.

The legislative nature of the approval can affect:

  • The adoption procedure;
  • The standard of judicial review;
  • Public participation;
  • Referendum rights;
  • Applicable litigation deadlines; and
  • The remedies available when adoption is challenged.

The Development Agreement Must Be Consistent With Applicable Planning Documents

Under Government Code Section 65867.5, a local legislative body generally cannot approve a development agreement unless it finds that the agreement is consistent with the general plan and any applicable specific plan.

Potential disputes may therefore involve alleged inconsistencies concerning:

  • Land use designations;
  • Density;
  • Development intensity;
  • Circulation;
  • Open space;
  • Infrastructure;
  • Specific plan requirements;
  • Building limitations; and
  • Other adopted planning policies.

A developer facing such a challenge should distinguish between an actual inconsistency and a disagreement over how broadly a planning policy should be interpreted.

Challenges to Adoption or Modification Can Have a Very Short Deadline

California Government Code Section 65009 establishes an unusually short limitation period for specified land use challenges.

An action seeking to attack, review, set aside, void, or annul a legislative body’s decision to adopt, amend, or modify a development agreement generally must be commenced and served on the legislative body within 90 days after the decision, subject to the statute’s provisions and exceptions.

This deadline can apply to challenges involving:

  • Original adoption;
  • An amendment;
  • A modification;
  • Associated procedural decisions; and
  • Related governmental acts within the statutory framework.

Businesses, neighboring owners, developers, and other interested parties should therefore evaluate potential development agreement challenges immediately rather than assuming ordinary contract limitation periods apply.

Contract Claims and Land Use Challenges Can Have Different Deadlines

A dispute about whether a local government properly adopted a development agreement is different from a later claim that a party breached an already valid agreement.

The applicable deadline can therefore depend on the nature of the claim.

For example:

  • A statutory challenge to adoption or amendment may fall under the short Government Code Section 65009 period;
  • A breach claim involving a written private development agreement may generally implicate California’s four-year written-contract limitations period;
  • A writ proceeding may involve separate procedural deadlines;
  • An environmental challenge may be governed by different statutes; and
  • A claim based on a later governmental action may accrue at a different time.

The cause of action should be identified before calculating any litigation deadline.

Annual Compliance Review Is Required for Statutory Development Agreements

Government Code Section 65865.1 requires local development agreement procedures to include periodic review at least every 12 months.

During that review, the applicant or successor in interest must demonstrate good faith compliance with the agreement.

Annual review can therefore become a critical moment for both the developer and local agency.

Potential review subjects may include:

  • Construction milestones;
  • Public improvement obligations;
  • Fee payments;
  • Infrastructure construction;
  • Affordable housing obligations;
  • Community benefits;
  • Reporting obligations;
  • Environmental mitigation;
  • Property maintenance;
  • Phasing requirements; and
  • Other contractual commitments.

Failure to Demonstrate Good Faith Compliance Can Threaten the Agreement

Under Section 65865.1, if the local agency determines on the basis of substantial evidence that the developer or successor has not complied in good faith with the agreement’s terms or conditions, the agency may terminate or modify the agreement.

This creates significant risk because termination may affect development rights on which the project’s financing and value depend.

A developer facing an adverse annual review should preserve evidence showing:

  • Work completed;
  • Payments made;
  • Permits obtained;
  • Infrastructure progress;
  • Government-caused delays;
  • Force majeure events;
  • Compliance correspondence;
  • Requested extensions;
  • Accepted performance; and
  • Any prior agency approvals or acknowledgments.

Good Faith Compliance Does Not Necessarily Require Perfect Performance

Development projects frequently span years and involve evolving circumstances.

A dispute may arise over whether an imperfect or delayed performance amounts to lack of good faith compliance.

Relevant considerations can include:

  • The seriousness of the breach;
  • Whether the obligation was material;
  • Whether performance remains possible;
  • Whether the developer attempted to cure;
  • Whether the agency contributed to the delay;
  • Whether the agreement permits extensions;
  • Whether substantial performance occurred; and
  • Whether the local agency previously accepted the developer’s performance.

Amendment and Cancellation Require Attention to Statutory Procedure

Government Code Section 65868 provides that a statutory development agreement may be amended or canceled, in whole or in part, by mutual consent of the parties or their successors in interest.

Notice must be provided in the manner required for development agreement consideration, and amendments are subject to the statutory approval provisions.

This means a developer and individual agency employee generally cannot simply rewrite major terms informally.

Material amendments may require:

  • Formal negotiation;
  • Public notice;
  • Planning review;
  • Legislative action;
  • Consistency findings;
  • An ordinance; and
  • Other required approvals.

Informal Government Assurances May Not Modify a Statutory Development Agreement

A developer may receive statements from planning staff, project managers, consultants, or other officials suggesting that a deadline or requirement will not be enforced.

Later disputes can arise when the developer contends those statements modified the agreement.

The analysis may involve:

  • Who made the statement;
  • Whether the person had authority;
  • Whether formal amendment procedures were required;
  • Whether the legislative body approved the change;
  • Whether the agreement contains integration or amendment provisions; and
  • Whether reliance on the statement was legally reasonable.

Material amendments should generally be documented through the formal procedure required by the agreement and governing law.

Recorded Development Agreements Can Bind Successors

Government Code Section 65868.5 requires a statutory development agreement to be recorded after the local agency enters into the agreement.

Once recorded, the agreement provides notice under California recording law, and its burdens and benefits generally bind successors in interest.

This can become critically important in:

  • Property sales;
  • Foreclosures;
  • Subdivision;
  • Transfers to affiliated entities;
  • Joint venture transactions;
  • Loan workouts;
  • Bankruptcy sales; and
  • Acquisition due diligence.

A Buyer Should Review Development Agreements Before Acquiring the Property

A purchaser may acquire valuable development rights but also substantial obligations.

Due diligence should evaluate:

  • The remaining agreement term;
  • Permitted development;
  • Outstanding public improvements;
  • Outstanding fees;
  • Annual review history;
  • Existing defaults;
  • Upcoming milestones;
  • Phasing requirements;
  • Reimbursement rights;
  • Assignment requirements;
  • Transfer restrictions;
  • Pending amendments; and
  • Government correspondence.

A buyer should not assume that acquiring the land alone guarantees that every development right remains in good standing.

Assignment Provisions Can Affect Project Transfers

Development agreements frequently address whether the developer may assign rights or obligations to another party.

Potential requirements may include:

  • Agency consent;
  • Assumption agreements;
  • Financial capability standards;
  • Partial assignments;
  • Release of the original developer;
  • Allocation among development phases;
  • Notice requirements;
  • Recordation; and
  • Continuing liability for specified obligations.

A property sale that ignores the development agreement’s assignment provisions can create disputes after closing.

Partial Assignments Can Be Especially Complicated in Master Developments

A master development may later be divided among several builders or parcel owners.

The parties may need to allocate obligations involving:

  • Infrastructure;
  • Roads;
  • Utilities;
  • Affordable housing;
  • Fees;
  • Open space;
  • Public facilities;
  • Environmental mitigation;
  • Transportation improvements; and
  • Community benefits.

The original agreement may need amendments or separate assignment and assumption agreements identifying which successor becomes responsible for each obligation.

Private Development Agreements Create Different Contractual Risks

Not every real estate development agreement involves a government entity.

Private development agreements can govern the relationship between the property owner and the party responsible for planning, entitling, financing, constructing, leasing, or selling the project.

These agreements may address:

  • Development management;
  • Project budgets;
  • Entitlement responsibilities;
  • Design;
  • Construction;
  • Financing;
  • Leasing;
  • Property sales;
  • Development fees;
  • Cost reimbursement;
  • Decision-making authority;
  • Reporting;
  • Project schedules;
  • Termination; and
  • Dispute resolution.

The Scope of the Developer’s Authority Should Be Clearly Defined

A private development agreement should identify which decisions the developer can make independently and which require owner or investor approval.

Major decisions may include:

  • Changing project scope;
  • Increasing the development budget;
  • Entering major construction contracts;
  • Hiring architects and engineers;
  • Changing design;
  • Obtaining financing;
  • Granting easements;
  • Approving substantial change orders;
  • Entering leases;
  • Selling project parcels; and
  • Settling litigation.

Unclear authority provisions can lead to disputes over whether the developer bound the owner to unauthorized obligations.

Entitlement Responsibilities Should Not Be Left Ambiguous

A private agreement may require the developer to obtain governmental approvals necessary for the project.

Those approvals may include:

  • Zoning approvals;
  • General plan amendments;
  • Specific plan approvals;
  • Conditional use permits;
  • Tentative maps;
  • Final maps;
  • Development agreements;
  • Design review;
  • Environmental approvals;
  • Building permits;
  • Grading permits; and
  • Utility approvals.

Disputes can arise over whether the developer promised to obtain a particular approval or merely agreed to use commercially reasonable efforts to pursue it.

An Obligation to Obtain Approval Is Different From an Obligation to Pursue Approval

Government approval is often outside the complete control of a private developer.

A development agreement should distinguish between:

  • A guaranteed result;
  • Reasonable efforts;
  • Commercially reasonable efforts;
  • Good faith pursuit;
  • A condition precedent; and
  • A discretionary business decision to discontinue the entitlement process.

If the contract merely requires reasonable efforts, failure to obtain the entitlement does not necessarily establish breach.

Project Budgets Are Common Sources of Conflict

Large developments evolve over time, and budgets can change because of:

  • Design revisions;
  • Material escalation;
  • Labor costs;
  • Interest rates;
  • Environmental requirements;
  • Utility upgrades;
  • Government fees;
  • Infrastructure obligations;
  • Change orders;
  • Tenant requirements;
  • Schedule delays; and
  • Unforeseen site conditions.

The agreement should establish who can revise the budget and what level of increase requires additional approval.

Cost Overruns Can Trigger Claims Against the Developer

An owner may allege that the developer exceeded the approved budget without authority.

The developer may respond that:

  • The increase was required to preserve the project;
  • The owner approved the work;
  • The agreement contained an emergency exception;
  • Costs resulted from owner-directed changes;
  • Government requirements changed;
  • The increase fell within approved contingency; or
  • The owner had contemporaneous knowledge and accepted the expenditure.

Budget histories, approvals, forecasts, invoices, and project correspondence can become central evidence.

Development Fees Can Be Disputed

A developer or development manager may receive compensation structured as:

  • A fixed fee;
  • A percentage of development costs;
  • A percentage of construction costs;
  • A monthly management fee;
  • An acquisition fee;
  • A financing fee;
  • A leasing fee;
  • A disposition fee;
  • An incentive fee; or
  • A combination of these structures.

Disputes can arise over which costs are included in the fee calculation and whether compensation continues after delay, suspension, or termination.

Affiliate Transactions Can Create Conflict-of-Interest Claims

A developer may retain affiliated contractors, consultants, brokers, or management companies.

The agreement should address whether affiliate transactions are permitted and what approval process applies.

Potential disputes may involve:

  • Undisclosed affiliate relationships;
  • Above-market fees;
  • Construction markups;
  • Brokerage commissions;
  • Procurement procedures;
  • Self-dealing;
  • Conflicts of interest; and
  • Failure to obtain required approval.

Financing Obligations Should Be Allocated Clearly

A development may fail even where land use approvals and construction plans are complete if financing is unavailable.

A private development agreement should identify responsibility for:

  • Equity;
  • Construction financing;
  • Permanent financing;
  • Loan applications;
  • Guaranties;
  • Financing fees;
  • Interest reserves;
  • Additional capital;
  • Cost overruns; and
  • Lender reporting.

Disputes frequently arise when one party believes the other promised to obtain financing but the agreement only required assistance with the financing process.

Development Agreements Should Coordinate With Loan Documents

A developer may possess authority under a private development agreement that is restricted by the project’s lender.

For example, the development agreement may authorize:

  • Major construction changes;
  • Property transfers;
  • Additional debt;
  • New leases;
  • Public easements; or
  • Project phasing changes.

The loan agreement may require lender consent to the same actions.

Approval under one agreement does not necessarily satisfy requirements under the other.

Construction Agreements Must Also Be Coordinated With the Development Agreement

Development disputes often overlap with construction disputes.

The development agreement should be coordinated with:

  • The general contract;
  • Architect agreements;
  • Engineering contracts;
  • Construction management agreements;
  • Major consultant agreements;
  • Infrastructure contracts;
  • Utility agreements; and
  • Public improvement contracts.

A developer may be responsible to an owner for delivering the project on one schedule while the construction contract provides the contractor with additional time.

Those inconsistent obligations can create significant exposure.

Project Milestones Should Be Objective Where Possible

Development agreements may establish milestones for:

  • Entitlement applications;
  • Permit issuance;
  • Financing;
  • Construction commencement;
  • Substantial completion;
  • Infrastructure completion;
  • Tenant delivery;
  • Final completion;
  • Property sale; and
  • Other phases.

Disputes become more likely when terms such as “completion,” “approval,” or “project readiness” are not defined.

Delay Claims Often Involve Multiple Causes

Development delays rarely result from only one event.

Potential causes include:

  • Government processing;
  • Environmental review;
  • Utility delays;
  • Design changes;
  • Owner decisions;
  • Financing;
  • Contractor delay;
  • Labor shortages;
  • Material shortages;
  • Weather;
  • Litigation;
  • Community opposition;
  • Unexpected site conditions; and
  • Changes in law.

A party seeking delay damages may need to establish not merely that the project finished late but that the opposing party’s contractual breach caused a particular period of critical delay.

Force Majeure Clauses Can Affect Development Deadlines

A force majeure provision may extend deadlines when performance is prevented by specified events outside a party’s reasonable control.

Potential events can include:

  • Natural disasters;
  • Government shutdowns;
  • Labor disruptions;
  • Utility interruptions;
  • War;
  • Specified supply shortages;
  • Litigation;
  • Governmental delay; or
  • Other events identified by the contract.

The language should be reviewed carefully because financial hardship, interest rate increases, or general market changes may not qualify unless the agreement specifically addresses them.

Notice Requirements Can Determine Whether Delay Relief Is Available

A contract may require a party seeking additional time to provide written notice within a specified period.

The notice may need to identify:

  • The delaying event;
  • The date it began;
  • The obligation affected;
  • The estimated duration;
  • Mitigation efforts; and
  • The extension requested.

A party can have a legitimate delay but still face a waiver argument if it ignored contractual notice requirements.

Conditions Precedent Can Determine Whether Performance Was Required

Some development obligations arise only after specified conditions occur.

Potential conditions precedent can include:

  • Acquisition of the property;
  • Government approval;
  • Environmental clearance;
  • Financing;
  • Approval of a project budget;
  • Execution of construction contracts;
  • Utility capacity;
  • Subdivision;
  • Tenant commitments; or
  • Other specified events.

A party accused of failing to perform may defend by showing that the contractual condition triggering the obligation never occurred.

Approval Rights Can Become a Source of Deadlock

Private development agreements often give owners or investors approval rights over major project decisions.

Disputes may arise when one party argues that approval was unreasonably withheld.

The agreement should be reviewed to determine whether approval is:

  • Solely discretionary;
  • Subject to reasonable consent;
  • Subject to objective standards;
  • Deemed granted if no response is provided; or
  • Required only for specified major decisions.

The wording of the approval standard can materially affect the claim.

Deadlock Procedures Can Preserve a Project

A development project can lose significant value if disputes prevent decisions concerning financing, construction, leasing, or government approvals.

Agreements may address deadlock through:

  • Escalation to senior management;
  • Mediation;
  • Expert determination;
  • Arbitration;
  • Buy-sell procedures;
  • Removal of the developer;
  • Forced property sale; or
  • Other negotiated mechanisms.

Using the contractual deadlock mechanism can sometimes preserve substantially more project value than immediate litigation.

Transfer and Assignment Restrictions Can Affect Private Agreements

A developer may want to transfer its rights to an affiliate, new joint venture, institutional investor, or purchaser.

The agreement may require:

  • Owner consent;
  • Financial qualifications;
  • An assumption agreement;
  • Release conditions;
  • Notice;
  • Continued guaranties;
  • Payment of transfer fees; or
  • Approval of the proposed successor.

An unauthorized transfer can potentially create a default even when the underlying development continues without interruption.

Termination Rights Should Be Distinguished From Ordinary Breach Remedies

A development agreement may permit termination after specified events.

Those events may include:

  • Material breach;
  • Failure to cure;
  • Failure to obtain entitlements;
  • Failure to obtain financing;
  • Failure to commence construction;
  • Missed completion milestones;
  • Bankruptcy;
  • Unauthorized transfer;
  • Abandonment; or
  • Other defined events.

The right to terminate should not automatically be assumed from the existence of any breach. The agreement may require a material breach, written notice, and an opportunity to cure.

Cure Provisions Can Prevent Premature Termination

A development agreement may provide different cure periods for different types of defaults.

A monetary default may require prompt payment.

A nonmonetary default may require additional time where cure cannot reasonably be completed within the initial period, provided the defaulting party begins corrective action and proceeds diligently.

Disputes may focus on:

  • Whether notice was adequate;
  • When the cure period began;
  • Whether the breach was curable;
  • Whether cure was timely commenced;
  • Whether the cure was completed diligently; and
  • Whether termination occurred prematurely.

Wrongful Termination Can Produce Significant Damages

Termination of a development relationship can disrupt a project that has already consumed significant capital.

A wrongfully terminated developer may claim losses involving:

  • Unpaid development fees;
  • Reimbursable costs;
  • Lost contractual compensation;
  • Lost incentive fees;
  • Investment losses;
  • Financing costs;
  • Project delay;
  • Lost opportunities; and
  • Other damages permitted by the agreement and California law.

The opposing party may contend that claimed future compensation is speculative or was dependent on milestones that would never have been achieved.

Damages Must Be Connected to the Breach

California Civil Code Section 3300 generally measures contract damages by the detriment proximately caused by the breach or likely to result from it in the ordinary course of events.

Development disputes can involve claimed damages such as:

  • Additional carrying costs;
  • Construction escalation;
  • Additional financing costs;
  • Lost rents;
  • Lost development fees;
  • Lost property value;
  • Re-entitlement costs;
  • Consultant expenses;
  • Infrastructure costs;
  • Lost sale proceeds; and
  • Other project-specific losses.

The claimant must establish causation rather than simply showing that the overall project became less profitable.

Lost Profit Claims Can Be Difficult in Development Litigation

A proposed development may not yet generate revenue when the alleged breach occurs.

A party claiming lost profits may need evidence concerning:

  • Project approvals;
  • Construction feasibility;
  • Financing;
  • Expected development cost;
  • Expected rents;
  • Expected absorption;
  • Market capitalization rates;
  • Expected sale prices;
  • Comparable developments; and
  • Probability of project completion.

The more speculative the future development, the more difficult it may be to establish lost profits with sufficient certainty.

Consequential Damage Waivers Can Limit Recovery

Private development agreements frequently restrict recovery of categories such as:

  • Consequential damages;
  • Special damages;
  • Indirect damages;
  • Lost profits;
  • Loss of opportunity; or
  • Punitive damages.

Litigation may then focus on whether a particular development loss is a direct contract damage or a barred consequential loss.

Specific Performance May Be Important Where Money Damages Are Inadequate

Some development obligations involve unique property rights or transactions that cannot easily be replaced with money.

A party may seek specific performance in appropriate circumstances involving obligations such as:

  • Transfer of real property;
  • Execution of agreed easements;
  • Performance of a land conveyance;
  • Release of development rights;
  • Execution of required project documents; or
  • Other sufficiently definite contractual obligations.

Specific performance is an equitable remedy and is not automatically available for every breach.

Declaratory Relief Can Clarify Development Rights Before the Project Fails

A party may seek a judicial determination concerning disputed contractual rights without waiting for the entire project to collapse.

Declaratory relief may address issues such as:

  • Whether an agreement remains effective;
  • Whether a party is in default;
  • Whether an extension was valid;
  • Whether an assignment is permitted;
  • Whether an approval can be withheld;
  • Whether an obligation has been satisfied;
  • Whether a milestone deadline was extended; or
  • Whether a termination right exists.

Injunctive Relief Can Be Critical When Development Rights Are Threatened

Some development disputes involve threatened actions that may be difficult to reverse after they occur.

A party may seek injunctive relief in appropriate circumstances to prevent:

  • Termination of development rights;
  • Unauthorized property transfer;
  • Unauthorized financing;
  • Transfer of project funds;
  • Interference with governmental approvals;
  • Recording of disputed documents;
  • Destruction of project records; or
  • Other threatened irreparable harm.

The party seeking an injunction must satisfy the applicable standards for extraordinary equitable relief.

Government Development Agreement Disputes May Require Writ Relief

When the dispute challenges governmental action rather than merely seeking damages under a private contract, the appropriate remedy may involve administrative or mandate proceedings.

Potential challenges may concern:

  • Adoption of the agreement;
  • Amendment;
  • Modification;
  • Termination after annual review;
  • Consistency findings;
  • Agency procedure;
  • Application of later development standards; or
  • Another governmental decision affecting the agreement.

The applicable claim, administrative record, standard of review, and filing deadline should be analyzed immediately.

Administrative Records Can Determine the Outcome of Public Development Agreement Litigation

Where a court reviews a local agency’s development agreement decision, the administrative record may contain much of the evidence relevant to the challenge.

That record can include:

  • Staff reports;
  • Planning commission materials;
  • Public comments;
  • Hearing transcripts;
  • Project applications;
  • Environmental documents;
  • Development agreement drafts;
  • Agency findings;
  • Correspondence;
  • Technical reports; and
  • Legislative records.

Parties should therefore present material objections and supporting evidence during the public process rather than assuming every issue can be raised for the first time in court.

Environmental Review Can Intersect With Development Agreement Disputes

Approval or amendment of a development agreement may occur alongside environmental review and other project approvals.

Disputes can arise concerning:

  • Environmental impact analysis;
  • Mitigation obligations;
  • Project changes;
  • Subsequent approvals;
  • Changed circumstances;
  • Infrastructure impacts;
  • Transportation;
  • Water supply;
  • Air quality; and
  • Other environmental issues.

Environmental claims can involve separate statutes, administrative procedures, and short litigation deadlines, so they should not be treated simply as ordinary breach-of-contract claims.

Conditions of Approval and Development Agreement Obligations Should Be Reconciled

A project may be subject simultaneously to:

  • A development agreement;
  • A tentative map;
  • A conditional use permit;
  • A specific plan;
  • Design review conditions;
  • Environmental mitigation measures;
  • Subdivision conditions;
  • Infrastructure agreements; and
  • Building permit requirements.

Disputes may arise when these documents appear inconsistent.

The developer should determine which obligation controls, whether the development agreement expressly incorporates another approval, and whether later conditions conflict with vested contractual rights.

Development Agreements Do Not Automatically Guarantee Every Later Permit

A development agreement may preserve specified uses and development standards while leaving later permit decisions subject to additional review.

The agreement itself may expressly preserve discretion concerning:

  • Detailed design;
  • Building permits;
  • Engineering;
  • Subdivision implementation;
  • Utility design;
  • Environmental mitigation;
  • Public safety requirements; and
  • Other later-stage approvals.

A developer should distinguish between vested development parameters and approvals that remain genuinely discretionary.

Public Benefit Obligations Can Become Material Disputes

Many large development agreements include negotiated benefits beyond ordinary land use approvals.

Potential obligations can include:

  • Affordable housing;
  • Public parks;
  • Community facilities;
  • Local hiring commitments;
  • Transportation improvements;
  • Public art;
  • Infrastructure funding;
  • Open space;
  • Economic development commitments; and
  • Other community benefits.

The parties may disagree over timing, valuation, completion standards, credits, substitutions, or whether later changed circumstances justify modification.

Fee Disputes Can Affect Development Economics

A development agreement may specify fees or establish procedures governing project-related financial obligations.

Disputes can involve:

  • Development impact fees;
  • Infrastructure fees;
  • Processing fees;
  • Affordable housing payments;
  • Transportation contributions;
  • Credits;
  • Reimbursement rights; and
  • Later fee increases.

Whether a later fee applies may depend on the development agreement’s wording, applicable law, and whether the fee conflicts with protected contractual rights.

Subdivision and Phasing Issues Can Create Long-Term Disputes

Large projects are often built over multiple phases and may be subdivided into separate parcels.

Development agreements may allocate obligations based on:

  • Specific phases;
  • Building permits;
  • Certificates of occupancy;
  • Parcel sales;
  • Unit counts;
  • Infrastructure milestones;
  • Development intensity; or
  • Other triggers.

Years later, successors may disagree over which parcel is responsible for an obligation that was originally drafted for the entire master project.

Successor Liability Should Be Addressed During Parcel Sales

A master developer selling individual parcels should determine whether development agreement obligations:

  • Run with the land;
  • Remain with the master developer;
  • Are assumed by the parcel buyer;
  • Require local agency approval;
  • Are allocated by phase;
  • Require financial security; or
  • Remain jointly enforceable.

Clear assignment and assumption documentation can prevent later disputes among project successors.

Development Agreement Rights Can Affect Property Financing

Lenders financing a development may place substantial value on the project’s development agreement.

Financing diligence may examine:

  • The remaining term;
  • Protected development rights;
  • Annual compliance status;
  • Outstanding developer obligations;
  • Default notices;
  • Assignment provisions;
  • Lender cure rights;
  • Termination rights;
  • Infrastructure requirements; and
  • Whether foreclosure would affect the agreement.

An unresolved development agreement default can impair financing even before the local agency formally terminates the agreement.

Lender Cure Rights Can Preserve a Distressed Development

Some agreements give lenders or secured creditors rights to receive default notices and cure developer defaults.

This can be important when the lender is considering:

  • Foreclosure;
  • Appointment of a receiver;
  • Replacement of the developer;
  • Sale of the loan;
  • Project completion;
  • A deed in lieu; or
  • A loan workout.

A lender acquiring control of a distressed project should confirm that development agreement rights have not been lost through an uncured default.

Bankruptcy Can Complicate Development Agreement Rights

A developer or property-owning entity may file bankruptcy while significant development obligations remain outstanding.

Potential issues can involve:

  • Executory contract treatment;
  • Assumption or rejection issues;
  • Automatic stay;
  • Property sales;
  • Assignment;
  • Municipal regulatory authority;
  • Infrastructure obligations;
  • Claims for damages; and
  • Lender rights.

Bankruptcy issues are governed primarily by federal law and require analysis separate from ordinary California contract and land use remedies.

Written Contract Claims Generally Carry a Four-Year California Limitations Period

For private development agreements and contractual claims founded on written instruments, California Code of Civil Procedure Section 337 generally provides a four-year limitations period.

The accrual date can depend on:

  • The date of breach;
  • The deadline for performance;
  • Termination;
  • Failure to make payment;
  • Failure to transfer property;
  • Failure to obtain required approval;
  • Repudiation; or
  • Other circumstances creating the contractual claim.

This general rule should not be confused with the much shorter deadlines that can apply to challenges involving governmental adoption, amendment, modification, environmental approval, or other land use decisions.

Attorney’s Fee Clauses Can Materially Affect Development Litigation

Development agreements frequently contain provisions allowing recovery of attorney’s fees incurred to enforce contractual rights.

California Civil Code Section 1717 generally makes contractual attorney’s fee provisions reciprocal in actions on the contract when the statute applies.

Potential fee exposure can include litigation involving:

  • Breach of contract;
  • Termination;
  • Payment obligations;
  • Development fees;
  • Property transfers;
  • Specific performance;
  • Declaratory relief; and
  • Other contract enforcement proceedings.

Attorney’s fee exposure can materially affect settlement strategy in a long-running development dispute.

Indemnity Provisions Can Shift Third-Party Risk

Development agreements may include indemnity obligations concerning claims arising from:

  • Construction;
  • Environmental conditions;
  • Contractors;
  • Design professionals;
  • Property operations;
  • Government approvals;
  • Third-party litigation;
  • Public improvements;
  • Personal injury; and
  • Other project risks.

Indemnity should be analyzed separately from a direct breach claim because different notice, defense, and allocation provisions may apply.

Insurance Requirements Can Become Part of the Dispute

Development agreements may require specified insurance throughout the project.

Requirements can include:

  • Commercial general liability;
  • Builder’s risk;
  • Professional liability;
  • Environmental coverage;
  • Workers’ compensation;
  • Automobile liability;
  • Property coverage; and
  • Additional insured endorsements.

Failure to maintain required coverage can create a contractual default and significantly increase project exposure after a loss.

Settlement Should Address the Future of the Project

Real estate development disputes differ from many ordinary contract cases because the underlying project may still have substantial unrealized value.

A settlement may therefore include more than payment of damages.

Potential solutions can include:

  • Extension of development deadlines;
  • Modification of project scope;
  • Additional development rights;
  • Revised infrastructure obligations;
  • Additional financing;
  • Transfer to a replacement developer;
  • Reallocation of project costs;
  • Revised phasing;
  • Property sale;
  • Buyout of a development partner;
  • New reimbursement procedures; or
  • Mutual releases.

A business resolution that preserves the development can sometimes produce substantially greater value than a damages judgment after the project fails.

Amendment Can Be Preferable to Termination

Changes in financing markets, construction costs, demand, or regulation may make the original development plan impractical even though the property remains developable.

The parties may consider amending:

  • Project phasing;
  • Milestone dates;
  • Building types;
  • Infrastructure timing;
  • Public benefits;
  • Financial obligations;
  • Reimbursement procedures;
  • Development management terms; or
  • Assignment provisions.

For statutory development agreements, any amendment must comply with the applicable formal approval requirements.

Document Preservation Is Critical in Development Agreement Litigation

Development projects can span many years, making document preservation particularly important.

Relevant evidence may include:

  • The executed development agreement;
  • Draft agreements;
  • Amendments;
  • Assignment agreements;
  • Purchase agreements;
  • Loan documents;
  • Government approvals;
  • Planning commission records;
  • City council or board records;
  • Environmental documents;
  • Annual review reports;
  • Compliance determinations;
  • Construction contracts;
  • Development budgets;
  • Infrastructure records;
  • Invoices;
  • Reimbursement requests;
  • Project schedules;
  • Emails;
  • Text messages;
  • Meeting minutes;
  • Consultant reports; and
  • Records concerning extensions or claimed defaults.

Draft History Can Help Explain Ambiguous Terms

Development agreements are often heavily negotiated.

Successive drafts may show how language concerning:

  • Project duration;
  • Extension rights;
  • Infrastructure;
  • Fees;
  • Reimbursement;
  • Assignment;
  • Development standards;
  • Termination;
  • Public benefits; or
  • Other disputed terms

changed during negotiation.

Whether draft history is admissible or useful depends on the particular contract interpretation issue and applicable evidentiary rules.

A Detailed Project Chronology Can Clarify Liability

A development dispute often becomes easier to evaluate after creating a timeline showing:

  • Property acquisition;
  • Original application;
  • Environmental review;
  • Development agreement negotiation;
  • Public hearings;
  • Agreement adoption;
  • Recordation;
  • Entitlement approvals;
  • Financing;
  • Construction commencement;
  • Infrastructure work;
  • Annual reviews;
  • Government notices;
  • Project delays;
  • Requested amendments;
  • Assignment attempts;
  • Default notices;
  • Cure attempts; and
  • Termination or litigation.

The chronology can show whether one party’s alleged breach actually preceded the project failure or occurred only after other problems had already made performance impossible.

Expert Evidence May Be Necessary

Depending on the dispute, expert testimony may be useful concerning:

  • Real estate valuation;
  • Development economics;
  • Construction scheduling;
  • Construction costs;
  • Infrastructure costs;
  • Land use planning;
  • Environmental matters;
  • Project finance;
  • Accounting;
  • Market demand;
  • Lost profits; and
  • Other damages.

For example, a party alleging that a wrongful termination destroyed project value may need to establish what the project was actually worth at the time and whether completion remained economically feasible.

Businesses Should Evaluate Development Economics Before Escalating the Dispute

A strong legal position does not necessarily mean that full litigation produces the best business outcome.

The parties should understand:

  • Current property value;
  • Existing debt;
  • Remaining development costs;
  • Outstanding infrastructure obligations;
  • Entitlement status;
  • Remaining agreement term;
  • Construction costs;
  • Financing availability;
  • Expected rental or sale revenue;
  • Market conditions;
  • Potential litigation costs; and
  • Whether a replacement development plan remains feasible.

These economic realities can determine whether amendment, settlement, transfer, or litigation is the most valuable remedy.

Careful Drafting Can Reduce Future Development Disputes

Development agreements can reduce uncertainty only when the agreement itself clearly allocates project risk.

Important subjects to address include:

  • Duration;
  • Extension rights;
  • Permitted uses;
  • Development intensity;
  • Project phasing;
  • Milestones;
  • Infrastructure responsibilities;
  • Public improvements;
  • Reimbursement;
  • Government fees;
  • Development standards;
  • Assignment;
  • Successor obligations;
  • Lender rights;
  • Force majeure;
  • Notice;
  • Cure;
  • Termination;
  • Indemnity;
  • Insurance;
  • Dispute resolution; and
  • Attorney’s fees.

Did You Know?

California statutory development agreements are not merely private contracts with a city or county. Government Code Section 65867.5 classifies them as legislative acts that must be approved by ordinance, while Section 65865.1 requires periodic compliance review at least every 12 months. A qualifying challenge to adoption, amendment, or modification can also be subject to the 90-day filing and service period in Government Code Section 65009.

Protecting Development Rights When Agreement Disputes Arise

Real estate development agreement disputes can involve vested development rights, land use regulations, public infrastructure, government fees, project milestones, financing, private development management, assignments, successors, annual compliance reviews, termination, and project damages. The appropriate strategy depends on whether the dispute arises from a statutory development agreement with a public agency, a private contractual relationship, or both. Because land use challenges may carry extremely short deadlines while development projects continue losing value during delay, parties should identify the governing agreement, preserve the project record, evaluate contractual and administrative remedies, and address potential disputes before key development rights are lost.

Putterman Law represents property owners, developers, investors, businesses, and other commercial real estate participants in disputes involving development agreements, land use rights, development projects, real estate contracts, project financing, and related litigation.

Learn more about real estate law services at Putterman Law

FAQs

What is a California statutory development agreement?

A statutory development agreement is an agreement authorized by Government Code Sections 65864 through 65869.5 between a local government and a person holding a legal or equitable interest in real property. It can establish specified development rights and obligations concerning matters such as permitted uses, density, development standards, project duration, infrastructure, and public improvements.

Does a California development agreement protect a project from later zoning changes?

Potentially. Government Code Section 65866 generally provides that specified rules, regulations, and official policies concerning permitted uses, density, design, improvements, and construction standards are those in effect when the agreement is executed unless the agreement provides otherwise. Later nonconflicting rules may still apply, and subsequent state or federal law can require modification or suspension of conflicting agreement provisions.

Can a city terminate a development agreement for developer noncompliance?

Potentially. Government Code Section 65865.1 requires periodic review at least every 12 months. If the local agency determines on substantial evidence that the developer or successor has not complied in good faith with the agreement’s terms or conditions, the agency may modify or terminate the agreement subject to applicable procedures.

Can a development agreement be amended?

Yes. Government Code Section 65868 permits amendment or cancellation of a statutory development agreement, in whole or in part, by mutual consent of the parties or their successors in interest. Statutory notice and approval procedures apply to amendments.

Does a statutory development agreement bind a purchaser of the property?

Generally, recorded statutory development agreements can bind successors in interest. Government Code Section 65868.5 provides for recordation and states that the burdens and benefits of the agreement generally pass to successors. Buyers should therefore review the agreement and its compliance history during due diligence.

How long does someone have to challenge adoption of a California development agreement?

Government Code Section 65009 generally requires an action attacking, reviewing, setting aside, voiding, or annulling a legislative body’s decision to adopt, amend, or modify a development agreement to be commenced and served on the legislative body within 90 days after the decision, subject to the statute’s provisions and exceptions.

What are common disputes under private real estate development agreements?

Common private disputes involve project budgets, development fees, entitlement responsibilities, financing, construction milestones, cost overruns, affiliate transactions, owner approval rights, assignments, development delays, termination, reimbursement, and claims that a developer exceeded contractual authority.

Can a developer recover damages if a development agreement is breached?

Potentially. Recoverable damages depend on the agreement, the nature of the breach, causation, contractual limitations, and applicable California law. Claims may involve unpaid fees, additional project costs, financing expenses, delay damages, lost development value, or other legally recoverable losses.

Can a court order specific performance of a development agreement?

Specific performance may be available for certain sufficiently definite contractual obligations when the applicable equitable requirements are satisfied and money damages are inadequate. Whether that remedy is available depends on the obligation, parties involved, and nature of the agreement.

What records are most important in a real estate development agreement dispute?

Important records can include the agreement and amendments, assignment documents, governmental approvals, annual compliance reviews, public hearing records, project schedules, budgets, construction contracts, infrastructure records, financing documents, reimbursement requests, default notices, extension requests, consultant reports, emails, meeting minutes, and documents showing performance of disputed obligations.

This article is for general information purposes and is not intended to be and should not be taken as legal advice.

Facing legal challenges? Putterman Law will help you win the day! Fill out one of the intake forms below or give us a call at (949) 271-6382 for legal help.

Facing Legal Challenges?

Putterman Law Will Help You Win The Day.

By clicking on the appropriate button below, you will be linked to our intake forms to begin the process.

If you only need general counsel, click “I Need General Counsel.” If you are in the process of litigation, choose “I Am Currently in Litigation.”